Collaboration that Drives Data Centre Delivery: From Fast-Tracking MEP & End-User Negotiations to As-Builts

10/22/2025

image cover

Recognised today as the “fifth utility” alongside water, electricity, gas, and telecommunications, data centres have become essential to modern infrastructure. The global data centre construction pipeline is forecast to peak at USD$92.5billion in 2026 (source: GlobalData). While this represents a slight slowdown from 2025, long-term investment is expected to grow significantly, driven by the surge in cloud computing, artificial intelligence, and digital services that will continue to increase global data traffic over the next decade (source: GlobalData).
 

Data centres are among the most technically complex and time-critical projects in the built environment. They demand precise coordination, robust engineering solutions, and rapid delivery to meet operational and commercial imperatives.

Governments and industry stakeholders are increasingly focused on balancing these demands with sustainability and land-use priorities. For example, Singapore’s Green Data Centre Roadmap encourages developers to address environmental impacts and resource availability—particularly water and energy—when selecting sites. In other regions, competing pressures on land use is forcing decision-makers to weigh the need for digital infrastructure against essential uses such as housing.

Whether delivering a new greenfield facility, as-built documentation, or repurposing an existing asset, success hinges on the seamless integration of architectural and engineering expertise. This is where specialised multidisciplinary collaboration with a partner such as Atlas helps clients navigate complexity, accelerate programmes, and ensure quality outcomes.

Case in point: Collaboration to Fast-Track MEP Detailed Design

The delivery of a new greenfield facility in Malaysia was underway, and our client was seeking, at short notice, a delivery partner to fast-track the MEP detailed design stage during their annual holiday season. Due to an increase in the data centre’s capacity, modifications were required to the MEP external services such as HV, LV, telecom, HVAC, fire protection and water supply.

Atlas rapidly mobilised a specialist MEP team to provide a fully integrated BIM delivery solution with clash coordination and resolution support. From the client supplied 60% detailed design stage MEP BIM model, it was up to our MEP engineers and technicians to deliver from this a 90% LOD 300 model and 2D documentation.

By leveraging our MEP BIM expertise, the client successfully met their programme—even during their annual holiday period—while maintaining quality and coordination.

Case in point: Collaboration to Accelerate End-User Negotiations

Our client in North America was transforming an existing two-storey commercial building into a state-of-the-art data centre. This required significant building works, including extending the existing structure, partially raising the roof, and undertaking a full interior refurbishment to accommodate the technical and operational demands of the proposed new facility.

To support negotiations with end-users, test-fit proposals were required to demonstrate how the space could be configured and function in practice. 
Working to a tight timeframe, our multidisciplinary team created a detailed BIM model and developed, and test fitted multiple design options in parallel to providing full MEP services design. 

High-quality presentation drawings enabled the client to present a range of well-considered proposals to their end-user within the demanding timeframe.

Case in point: Collaboration to Digitise Existing Data Centres

To support the digitisation of two existing data centre buildings, our client required the creation of accurate as-built BIM models within a tight timeframe. With no existing BIM models available, the 3D models had to be built from scratch.

From hundreds of supplied PDF and as-built CAD (dwg) drawings, Atlas developed 3D models from the ground up. With a dedicated team of six engineers and technicians we delivered the first data centre model in six weeks, while a team of four completed the second in eight weeks.
The resulting fully-integrated LOD 200 – 300 as-built models incorporate architectural, interior architecture, structural, and MEPF elements, providing a comprehensive digital representation of both facilities.

 

These case studies highlight how effective collaboration with a flexible delivery partner can make the difference between programme-critical milestones and falling short. Whether accelerating negotiations with end-users through rapid design options or fast-tracking technical delivery during a period of reduced capacity, Atlas’ ability to integrate seamlessly with client teams ensures data centre projects maintain momentum without compromising quality. In an industry where time pressures and complexity are constant, our approach provides clients with the confidence and agility needed to deliver outcomes that stand up to both commercial and technical scrutiny.

Contact us to discuss how collaboration with Atlas helps drive project success.